BEST Test laboratory is equipped with the most advanced testing
facilities and is capable of conducting all tests required
by IEC standards except short circuit mechanical withstand
test, conducted in an independent international laboratory,
CESI-Italy.
Tests performed on the transformers can be classified as follows:
Tests during manufacturing, routine tests, type tests, special
tests, acceptance tests, site tests, defect analysis / identification
and tests before maintenance.
Tests during manufacturing:
Performed on all transformers after the active part assembly
completed
a) Winding resistance measurement
- after the coils are manufactured
- after the active part assembly completed.
b) Voltage ratio measurement and checking of the vector
group
c) D.C. insulation resistance control
Routine Tests:
Performed on all transformers according to TS 267,
IEC 76 etc. at the end of manufacturing process
a) Voltage ratio measurement and checking of the vector
group
b) Winding resistance measurement
c) Applied voltage test
d) Induced voltage test
e) No-load losses and no-load current measurement
f) Load losses and short-circuit voltage measurement
g) AC insulation loss factor and capacitance measurement
f) DC insulation resistance measurement
h) Measurement of voltage regulation and efficiency
Type Tests:
Performed upon customer request.
a) Temperature Rise Test
b) Impulse voltage withstand test
Special Tests:
Performed upon customer request.
a) Noise level measurement
b) No-load current and voltage harmonics measurement
c) Zero sequence impedance measurement
d) Partial discharge measurement
e) Transformer oil dielectric withstand measurement
f) AC insulation test of bushings
g) Fan losses measurement
h) On-load tap changer tests
i) Checking of protective and alarm equipment functions and
insulation
Acceptance Tests:
Performed according to the customer requirements at the
witness of the customer or his representative/s. Acceptance
tests are the ones required and chosen by the customer from
the above listed tests
Site Tests:
When the transformer is delivered to site and the montage
is completed. Site tests are performed before start-up upon
customer request.
Defect Analysis and tests before maintenance:
Performed for the defected transformers delivered to
our factory and also for the transformers for which the maintenance
is going to be done.
|
 |